Procedure:
1. Determine the rotary switch position for your country and purpose. Call up the Technical
Information "Overview of the Rotary Switch Settings" at www.SMA-Solar.com.
2.
Danger to life due to high voltages
Ensure that the inverter is disconnected from all voltage sources and that the enclosure lid
is removed (see Section10, page45).
3. Set the rotary switches A and B to the required
position using a flat-blade screwdriver (blade
width: 2.5mm).
The inverter will adopt the setting after commissioning. This can take up to five minutes.
7.3 Setting the NetID
By default, the NetID is set to 1 for all SMAinverters and SMAcommunication products with
BLUETOOTH. If your PV system consists of an inverter and a maximum of one further BLUETOOTH
device (e.g. computer with BLUETOOTH interface or SMAcommunication product), you can leave
the NetID set to 1.
You must change the NetID in the following cases:
If your PV system consists of one inverter and two other BLUETOOTH devices (e.g. computer
with BLUETOOTH interface and SMA communication product) or of multiple inverters with
BLUETOOTH, you must change the NetID of your PV system. This will enable communication
with multiple BLUETOOTH devices.
If another PV system with BLUETOOTH is located within 500m of your PV system, you must
change the NetID of your PV system. This will help keep both PV systems separate.
If you do not wish to communicate via BLUETOOTH, deactivate the BLUETOOTH
communication on your inverter. This will protect your PV system from unauthorized access.
7 Commissioning
SMA Solar Technology AG
Operating ManualSB30-50TL-21-BE-en-1132